Build Progress Wk8
- Details
Job Number NB001: Most of the Epoxy Runs within the inside of the hull have now been removed.
Job Number NB002: The Hog (inner keel) is now installed on the building frame and the frames have been glued in position to it.
The remaining larch for both boats has now been delivered to the shed. The Aprons and Stems for NB002 have been manufactured and are available to install.
Build Progress Wk7
- Details
Keel and stems installed. Job NB001 has been lifted off the moulds and is now in Bay B where it will now have the internal fit-out before turning up-side down again to have the outside hull painted. NB001 has now reached Milestone 2.
{youtube}jjZ0JcPdWqM{/youtube}
Build Progress Wk6
- Details
The planking is now complete on Job NB001. When the Keel and Stems are installed then the boat will be lifted off the moulds allowing Job NB002 to commence.
There is still some "fairing" (smoothing of planks) on some "flat spots" but this could be completed before the boat is painted while in Bay B of the shed.
Job Number NB002 The Frames have now been laminated (glued together) and are ready to be assembled when the building frame in Bay A is available.
Build Progress Wk5
- Details
Job Number NB001:
Planking is complete up to plank 4 on each side. This only leaves plank 5 and 6 on each side still to be installed.
Job Number NB002: All parts have now been cut from the sheets and the dressing of planks and frame parts is on-going.
Build Progress Wk4
- Details
The planking has commenced but there has been difficulty in installation of plank 2 as it did not want to sit on the moulds at the correct points. All the other builds are experiencing the same problem with even greater difficulty. We have now succeeded in installing it but a little "fairing" work will be required with "Long Boards" (long boards of plywood with 80 grit sandpaper attached).
The following work has been done this week: Both Garboard Planks installed. Port 2nd Plank installed. Starboard 2nd Plank cut and scarfed with rebates cut both fore and aft. This plank has been dry fitted (no glue applied), and is ready to be glued in position.