The planking is now complete on Job NB001. When the Keel and Stems are installed then the boat will be lifted off the moulds allowing Job NB002 to commence.

There is still some "fairing" (smoothing of planks) on some "flat spots" but this could be completed before the boat is painted while in Bay B of the shed.

Job Number NB002 The Frames have now been laminated (glued together) and are ready to be assembled when the building frame in Bay A is available.